Drawings Accepted
(5days)

Mold Manufacturing
(15days)

Injection
(2days)

Assembling
(1day)

Coating & Sanding
(10days)

Wax Removal
(1day)

Sand Shell Preheat
(0.5day)

Casting
(0.5day)

Sand Shell Removal
(2days)

Cutting
(1day)

Heat Treatment
(2days)

Machining/Enforcement
(5days)

Final Inspection
(5days)

Packing & Transport
 

 

Remarks:The above number of days are a normal manufacturing period and could be changed depending on the shape and the materials to be used.